GNIRS

August 2020 Call for Proposals

August 1st, 2020

Gemini North is accepting proposals for the Fast Turnaround (FT) program. We are not yet accepting proposals for Gemini South. Here, we give information specific to this proposal cycle. Please see the other FT pages - particularly the rules - for general information about the program. FT-specific proposal templates must now be used for all FT proposals; see the "PIT information" section below.

Announcements prior to 2020

January 1st, 2020

2018 Nov 26 - Dec 14

GNIRS was removed from the telescope to work on filter wheel #2 which had been showing increasing instances of not going into position reliably. The filter wheel datum switches were replaced on both filter mechanisms, a temporary light baffle was removed from wheel #1, and dust was removed from the filters using CO2 snow.

2018 Jun 20-25

Re-seated the detector controller boards, replaced the sequencer board, and replaced a voltage regulator. The read noise levels are now back to normal.

2018 Jun 5