Gemini South Semester 2025A
The semester calendar shows multi-instrument queue nights, priority visitor nights, scheduled classical runs and engineering or commissioning blocks. 
Horizontal rows represent instrument ports, color-coded to indicate instruments mounted. Instruments are available for science unless otherwise noted. 
Note: ToO PIs should always check the "what's available now" pages that are linked from the contents list for the most up-to-date information. 
Engineering or commissioning blocks are shown across all rows when no backup queue is available (or telescope is closed).
New and full moon dates are shown on the left.  Dates above each month are color-coded to show weekends (orange) and holidays (green)
Key:    GMOS   F2   IQUEYE   Canopus       GSAOI     Cal/ZORRO     GHOST   SHUTDOWN  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
February Port 1-up  GHOST               IQUEYE/C-1                                
12 full Moon Port 2   cal/ZORRO                                                    
27 new Moon Port 3   GMOS                                                      
  Port 4   Canopus                                                    
  Port 5   F2                                                        
  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
March Port 1-up  GHOST                                                          
13 full Moon Port 2   cal/ZORRO             ZORRO run                                        
28 new Moon Port 3   GMOS                                                          
  Port 4   Canopus                                                        
  Port 5   F2                                                            
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
April Port 1-up  GHOST         GSAOI             Laser run       GHOST              
12 full Moon Port 2   cal/ZORRO                                                      
27 new Moon Port 3   GMOS                                                        
  Port 4   Canopus                                                      
  Port 5   F2                                                          
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
May Port 1-up  GHOST     GSAOI             Laser run       GHOST                    
12 full Moon Port 2   cal/ZORRO           ZORRO run                                            
27 new Moon Port 3   GMOS                                                          
  Port 4   Canopus                                                        
  Port 5   F2                                                            
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
June Port 1-up  GHOST                                                        
10 full Moon Port 2   cal/ZORRO                                                      
25 new Moon Port 3   GMOS                                                        
  Port 4   Canopus                                                      
  Port 5                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
July Port 1-up  GHOST                                                            
10 full Moon Port 2   cal/ZORRO ZORRO run                                           Telescope            
24 new Moon Port 3   GMOS                                           Shutdown            
  Port 4   Canopus                                         A&G              
  Port 5   F2                                             Maintenance          
Version: Dec 13, 2024