Gemini North Semester 2024A -- Dates are local HST 
The semester calendar shows multi-instrument queue nights, engineering or commissioning. Dates are local HST, dates in red are weekends and holidays.  
Instruments potentially usable are indicated by the colored-horizontal bands (see color key below). 
"VIB" means work related to telescope vibration.
"long" means GNIRS will be configured to use long camera during Jul10-16.
Key: GMOS     GNIRS     NIFS     Altair     IGRINS2   Visiting   Engineering  
                 
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Feb GMOS                                                               Feb
  GNIRS                                                                
24 full NIFS/IG2                                                                
9 new Altair                                                                
  Visiting                                           MAROON-X    
                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Mar GMOS                                                               Mar                
  GNIRS                                                                                
24 full NIFS/IG2                                                                                
10 new Altair                                                                                
  Visiting MAROON-X ALOPEKE MAROON-X            
                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
Apr GMOS                                                               Apr
  GNIRS                               IRDC IRDC IRDC                            
8 new NIFS/IG2                                             comm comm comm comm comm comm comm      
23 full Altair                                                                
  Visiting MAROON-X                    
                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
May GMOS                                                               May
  GNIRS coldhead replacement work                                              
8 new NIFS/IG2                                                                
23 full Altair                                                                
  Visiting VIB VIB                                     ALOPEKE MAROON-X  
                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
June GMOS                                                               June
  GNIRS                                                                
7 new NIFS/IGRINS2NIFS/IG2                                                                
21 full Altair                                                                
  Visiting MAROON-X    
                                                             
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
July GMOS                                                               July
  GNIRS                   long long long long long long long                                
6 new NIFS/IG2                                 SV SV SV SV SV SV SV                  
21 full Altair                                                                
  Visiting MAROON-X               MAROON-X